en-US PSP Machinery - Successfully re-established cooperation with FLSmidth
Main page>News>Successfully re-established cooperation with FLSmidth

Successfully re-established cooperation with FLSmidth

After a two-year pause, a successful business relationship with the foreign customer FLSmidth was successfully established. The result is new mill contracts worth about 1.1 MEUR.

 

Both of the contracts are a challenge for our company and their successful completion will create the conditions for acquiring other projects of similar volume.

 

Pumpkin Hollow Project – Copper Processing Mine, Nevada, USA

• Mill SAG Ø 22' x 12' ; 2 x 180°

• Ball Mill Ø 15' x 22.5' ; 2 x 360°

Total weight: approx. 80 tons

Term of delivery: February 2019

 

Boliden Kevitsa Project – Minerals Processing Mine, Northern Finland

• Mill AG  Ø 32´x 32´; 6 x 180°

Total weight: approx. 250 tons

Term of delivery: April 2019

FLSmidth